Waste Heat Recovery Project Supporting the 420,000-ton-per-year Solid Waste Comprehensive Utilization Project of Jiangquzhou Jutai Building Materials Co., Ltd.


Release time:

2013-08-06

  The EPC general contracting project for the waste‑heat recovery system supporting the 420,000‑ton‑per‑year solid‑waste comprehensive utilization facility of Zhejiang Quzhou Jutai Building Materials Co., Ltd., undertaken by our company, successfully passed the owner’s 72‑hour performance acceptance test on July 19, 2013, with steam production meeting the design specifications. This project is a dedicated low‑temperature waste‑heat recovery unit designed to recover waste heat from the kiln‑head clinker cooler and the kiln‑tail preheater of Zhejiang Quzhou Jutai Building Materials Co., Ltd.’s 1,600 t/d clinker production line, delivering an annual steam output exceeding 93,600 tons.