Our company has undertaken a 6 MW pure low-temperature waste heat power generation project.
Release time:
2018-02-14
To ensure that the process conditions are finalized before the Spring Festival, enabling other disciplines to promptly produce drawings and meet the necessary requirements after the holiday, a kickoff meeting for the construction drawings of the 6 MW pure low-temperature waste heat power generation project (Project No. 18215), supporting the 2,500 t/d new dry-process clinker cement production line at Huaxin Cement (Tibet) Co., Ltd., was held on the afternoon of February 12, 2018, in the company’s fifth-floor conference room.
The 18215 project is located in Sangri County, Shannan Prefecture, Tibet, south of Lhasa and Nyingchi, near the China–India border and not far from the Doklam area.
Upon completion, the project will supply 2,500 tons of cement raw materials per day to support infrastructure development in the Tibet Autonomous Region. This represents a concrete step taken by our company to actively participate in the national Belt and Road Initiative.
Blog Highlights
[2024-08-07]